The project has a five-year timetable, from April 2022 through to March 2027. This will differ from the original proposal where updates to the project timetable have occurred during the project lifetime.
Month | WP0 | WP1 | WP2 | WP3 | WP4 | WP5 |
---|---|---|---|---|---|---|
2022-04 | ||||||
2022-05 | M0.1 | |||||
2022-06 | M2.1 | |||||
2022-07 | M1.1 | |||||
2022-08 | M3.1 | |||||
2022-09 | ||||||
2022-10 | ||||||
2022-11 | M5.1 | |||||
2022-12 | M2.2 | |||||
2023-01 |
M3.2 |
M4.1 | ||||
2023-02 | M0.2 |
M1.2 |
M2.3 |
|||
2023-03 | M2.4 | |||||
2023-04 | M5.2 | |||||
2023-05 | D2.1 | |||||
2023-06 | M3.5 | M4.2 | ||||
2023-07 | ||||||
2023-08 | ||||||
2023-09 | M3.6 | M5.3 | ||||
2023-10 | M3.7 | |||||
2023-11 | ||||||
2023-12 | ||||||
2024-01 | M3.4 | M4.3 | ||||
2024-02 | M0.3 | M1.3 | M2.10 | M5.4 | ||
2024-03 |
M2.5 |
|||||
2024-04 | M3.8 | D4.1 | ||||
2024-05 | M1.4 | D2.2 | ||||
2024-06 | ||||||
2024-07 | M1.5 | |||||
2024-08 | M3.9 | M5.5 | ||||
2024-09 | ||||||
2024-10 | D0.1 | D3.1 |
M4.4 |
D5.1 | ||
2024-11 | M0.4 | |||||
2024-12 | ||||||
2025-01 |
M3.10 |
|||||
2025-02 | M0.5 | M2.11 | M5.6 | |||
2025-03 |
M2.6 |
|||||
2025-04 |
M3.11 D3.3 |
M4.5 M4.6 |
||||
2025-05 | M1.7 | M5.7 | ||||
2025-06 | M2.17 | |||||
2025-07 | M1.6 |
M4.7 M4.8 |
||||
2025-08 | M5.8 | |||||
2025-09 | M2.18 | M3.12 | ||||
2025-10 | M3.15 |
M4.9 M4.10 |
D5.2 | |||
2025-11 | M5.9 | |||||
2025-12 | M2.19 | |||||
2026-01 |
M3.13 M3.14 D3.4 |
M4.11 D4.3 |
||||
2026-02 | M0.6 | M1.8 | M2.12 | M5.10 | ||
2026-03 |
M2.7 M2.15 M2.20 |
|||||
2026-04 |
M4.12 M4.13 |
|||||
2026-05 | M5.11 | |||||
2026-06 | M2.21 | |||||
2026-07 |
M1.9 D1.2 |
M3.16 |
M4.14 M4.15 |
|||
2026-08 | M5.12 | |||||
2026-09 | M3.17 | |||||
2026-10 | D0.2 | M2.22 | ||||
2026-11 | ||||||
2026-12 |
D1.3 D1.4 |
|||||
2027-01 |
D3.5 |
D4.4 | D5.3 | |||
2027-02 | M0.7 | |||||
2027-03 |
M2.8 M2.16 |